Please note that some of our online services will be unavailable on Friday 22 November from 7.00pm for approximately 3-4 hours due to planned system maintenance. Payments can still be made by internet banking (via your bank) while our online payment services are offline. If a service is unavailable, please retry after 11.00pm.

Glenorchy Water Treatment Upgrades

Delivery of a new UV water treatment solution in Glenorchy.

About the project

In response to the cryptosporidium outbreak that affected Queenstown’s water supply back in October 2023, we’re working to upgrade several treatment sites throughout the district to provide safe and fully compliant drinking water.

As part of these upgrades, we’re starting work in September 2024 to install a new UV treatment solution in Glenorchy, next to the tonwship’s existing water reservoirs.

We’ll also be upgrading the borefield on Glenorchy-Queenstown Road at the edge of the township.

Work will be carried out by Fulton Hogan with assistance from Veolia.


What's the latest?

3 September 2024

Crews will be starting work to install the new UV treatment solution up by the reservoir on Monday 16 September 2024.

Work at the borefield will follow in early October 2024.


What to expect

As with any construction project, minor disruptions should be expected while work is undertaken. This is likely to include some noise and construction machinery movements in the area, but these will be minimised as much as possible.

Shoulder closures will be required along part of Glenorchy-Queenstown Road near the entrance to Glenorchy once work begins on upgrades at the borefield, but this isn’t expected until early October.


Construction dates

Work to install the new UV treatment solution starts on Monday 16 September.

Upgrades at the borefield will begin in early October.

We expect all work to be completed by mid-November 2024.


Contact us

If you have any comments, questions, or concerns, please contact QLDC’s Services team on 03 441 0499 or email services@qldc.govt.nz